STH 69 Construction Project Update 9/22/22

Asphalt Paving has begun!

The following work is anticipated to finish up the project:

  • Asphalt Paving continues into early October
  • Aggregate Shoulder placement
  • Landscaping
  • Pavement Marking
  • Rumble Strips
  • Signing
  • Work between Diane Avenue and Henry Road continues in preparation for 2023
  • Utility work continues south of Paoli to Belleville

A reminder that CTH PB at STH 69 in Paoli is closed to all traffic.

Paoli Road is permanently removed from STH 69, and cul-de-sac’s are being built. 

STH 69 is closed to thru traffic.  Access is allowed for residents and businesses that have an origin or destination on the project. It is highly suggested to use your closest access to STH 69 to get to a driveway. Large trucks need to use appropriate truck routes.

Please slow down, be aware of the flaggers. The construction crew has the right-of-way.

A signed detour route is posted and follows WIS 92, WIS 78 and US 18/151.

Project Website:  https://projects.511wi.gov/wis69/

If you have any comments or questions, please reach out to Kim Ballweg at 608.212.5191 or ballwegk@AyresAssociates.com.

 

Thank you for your patience and understanding throughout the construction season. The section from Paoli to Verona is anticipated to open around November 1st.