On Saturday August 29th Payne & Dolan will start preparation for paving Speedway Road north of Schaller Road. They will be pulverising the existing pavement, and then grading and compacting it to make a suitable surface for paving. This process will take most of the day.
Sometime during the week of September 1, exact day TBD, they will pave the road with 2 1/2″ of asphalt 18′ wide. The exact date is not yet known, but will be posted here when it is known.
The town regrets the inconvenience of this process, but hopes that having a freshly paved road will make up for it.
Posted August 26, 2020.