Status Update: May 22 – May 26, 2017
STH 69 closed to through traffic on Monday, May 22.
Tree removals will begin on Tuesday, May 23 along with breaking the concrete pavement.
Pavement removal north of the bridge will begin later in the week and will continue into next week.
Details:
STH 69 work is scheduled from May 22, 2017 – August 31, 2017 and the road will remain closed to through traffic during this time frame. Access to local properties and businesses will be maintained at all times throughout construction. Work for this project will include concrete pavement removal, common excavation, water main and storm sewer installation, concrete bridge repairs, new asphalt pavement, curb and gutter removal and replacement, new guardrail, pavement marking, and other incidental items needed to complete the work.