Fall 2016 Update
The current project schedule is as follows:
- Public Involvement Meeting #3 – Spring 2017
- Environmental Document Submittal – Spring 2017
- Plat Approval/Real Estate Acquisition Begins – Summer 2017
- Final Plans – May 2019
- Construction – Spring-Fall 202o
Persons with any questions or concerns are encouraged to contact WisDOT Project Manager Mahesh Shrestha, 608-245-2674 or Mahesh.shrestha@dot.wi.gov